MNG00785 Project Management

Published : 25-Sep,2021  |  Views : 10

Question:

Develop an appropriate metric - this sets the target and expectation of all the stakeholders. It is important to determine a quantitative target that needs to be expressed as a metric in terms of an increase or decrease of money.Determine the timeframe for achieving the MOV - ask yourselves, when do we want to achieve this target metric

Define Scope and produce a Scope Management Plan Define the scope of the project and detail how the scope will be managed.Provide a list of Resources Identify and detail the resources for the project using MS Project where appropriate, including.

Answer:

The analysis of the various areas of influence for the project of “Development of the Ticketing System for RALS” has shown a critical review of strategy, financial, social, operational, and customers. These factors have crucial impact on the operations of the project. The following table would depict the impact of these factors,

Rank

Area of impact

Description

1st

Financial

The part of money related territory is exceptionally critical for the improvement of the project and its suggestion for the administration of the capacities. The examination would demonstrate the arrangement of the metaphorical improvement of the funds and their suggestion for the advancement of the last angles.

2nd 

Customer

The clients assume an essential part in adjusting the advancement of the viable and enhanced procedures. The client territory is a measure of the impact of the clients on the operations of the project. It would shape the possibility of building up the operations of the association.

3rd 

Operational

The operations of the task would have a tendency to infer the arrangement of the adequate organization of the project and its capacities. The RALS project would need to guarantee that the operations of the task would have a tendency to suggest the brilliant organization of operations.

4th 

Strategy

Business associations have been utilizing the business operation advancement by the assistance of keen and compelling procedure improvement. The technique territory would shape the combination of the steady administration of the operations for framing the investigation of the project.

5th 

Social

Project associations have been utilizing the development of the social upliftment and administration for guaranteeing the help of the legislature and neighbourhood group. The social zone helps in framing the administration of the operations for building up the authoritative procedure.

 o Better – Ticketing system created in the undertaking would help in conquering the administration of the operations for RALS and Globex. The change of the operations would help in basic assessment of the operations and capacities.

o Faster – Ticketing system created in the undertaking would help in enhancing the productivity of operations by basic assessment of the project mix and administration. The expanded pace of operations would help in conclusive administration of the operations.

o Cheaper – Ticketing system created in the project would help in shaping the simplicity of operations which would automatically diminish the general cost of the capacities of the administrations of RALS and Globex.

o Do more – Ticketing system created in the project would help in expanding the usefulness and part of building up the task operation.

 Part Two: Define Scope and produce a Scope Management Plan

Scope Definition: The project “Development of the Ticketing System for RALS” is developed for integrating the use of the information and formation of the improved ticketing system for the development of the operations. The project would involve the improvement of the operations of Globex for the RALS or Riverina Agricultural and Lifestyle Show.

Requirements:

The human requirements of the project of “Development of the Ticketing System for RALS” are Project Manager, Investment Manager, Project Sponsor, System Analyst, System Developer, Risk Analyser, Business Analyst, and System Tester.

The material requirements of the project of “Development of the Ticketing System for RALS” are computer devices, storage media, network components, raw materials, routers for network connection, and infrastructure.

In-scope and out of scope items of the project: The project plan, budget allocation, system design, implementation plan, and change management schemes are the inclusion and in scope items of the project. The development plan would be helpful for considering the involvement of the project integration and its significant management of the plan of operations. However, the transportation and communication plan are not a part of the project plan.

List of resources:

The resources used in the project of “Development of the Ticketing System for RALS” are given in the tables below 

The usage of the resources are given in the table below,

Resource Name

Work

Cost

Project Manager

768 hrs

$153,600.00

   Requirement Analysis

24 hrs

$4,800.00

   Specification of Project is Evaluated

32 hrs

$6,400.00

   Project Kick off meeting

32 hrs

$6,400.00

   Analysis of various vendors

32 hrs

$6,400.00

   Capability analysis of vendors

40 hrs

$8,000.00

   Budget Planning

40 hrs

$8,000.00

   Planning Schedule

32 hrs

$6,400.00

   Labor Management is planned

32 hrs

$6,400.00

   System Design is made

40 hrs

$8,000.00

   Milestone Requirements are formed

56 hrs

$11,200.00

   Implementing system designed

80 hrs

$16,000.00

   Requirement of design implemented

72 hrs

$14,400.00

   Risk Assessment

56 hrs

$11,200.00

   Risk Mitigation

48 hrs

$9,600.00

   Development of risk register

56 hrs

$11,200.00

   Risk Impact is modified

64 hrs

$12,800.00

   Success Evaluation of project

16 hrs

$3,200.00

   Final Project report is developed

16 hrs

$3,200.00

Investment Manager

40 hrs

$4,000.00

   Budget Planning

40 hrs

$4,000.00

Project Sponsor

152 hrs

$18,240.00

   Project Kick off meeting

32 hrs

$3,840.00

   Budget Planning

40 hrs

$4,800.00

   Initiation is built

48 hrs

$5,760.00

   Success Evaluation of project

16 hrs

$1,920.00

   Final Project report is developed

16 hrs

$1,920.00

System Analyst

552 hrs

$82,800.00

   Initiation is built

48 hrs

$7,200.00

   Milestone Requirements are formed

56 hrs

$8,400.00

   Implemening system designed

80 hrs

$12,000.00

   Implementation Phase modification

64 hrs

$9,600.00

   Equipments are verified

72 hrs

$10,800.00

   Reviewing the testing Phase

64 hrs

$9,600.00

   Entire plan is developed

56 hrs

$8,400.00

   Test result in executed

0 hrs

$0.00

   Risk Assessment

56 hrs

$8,400.00

   Development of risk register

56 hrs

$8,400.00

System Developer

528 hrs

$52,800.00

   Analysis of various vendors

32 hrs

$3,200.00

   System Design is made

40 hrs

$4,000.00

   Milestone Requirements are formed

56 hrs

$5,600.00

   Implementation Phase modification

64 hrs

$6,400.00

   Equipments are verified

72 hrs

$7,200.00

   Initiation of testing phase

40 hrs

$4,000.00

   Reporting the testing phase

8 hrs

$800.00

   Entire plan is developed

56 hrs

$5,600.00

   Test Plan is developed

72 hrs

$7,200.00

   Test result in executed

0 hrs

$0.00

   Recognition of risk factors

40 hrs

$4,000.00

   Risk Mitigation

48 hrs

$4,800.00

Risk Analyzer

216 hrs

$19,440.00

   Recognition of risk factors

40 hrs

$3,600.00

   Risk Assessment

56 hrs

$5,040.00

   Development of risk register

56 hrs

$5,040.00

   Risk Impact is modified

64 hrs

$5,760.00

Business Analyst

152 hrs

$15,200.00

   Specification of Project is Evaluated

32 hrs

$3,200.00

   Project Kick off meeting

32 hrs

$3,200.00

   Capability analysis of vendors

40 hrs

$4,000.00

   Planning Schedule

32 hrs

$3,200.00

   Final Project report is developed

16 hrs

$1,600.00

System Tester

344 hrs

$27,520.00

   Equipments are verified

72 hrs

$5,760.00

   Initiation of testing phase

40 hrs

$3,200.00

   Reporting the testing phase

8 hrs

$640.00

   Reviewing the testing Phase

64 hrs

$5,120.00

   Test Plan is developed

72 hrs

$5,760.00

   Test result in executed

0 hrs

$0.00

   Recognition of risk factors

40 hrs

$3,200.00

   Risk Mitigation

48 hrs

$3,840.00

Part Three: Project Plan

The project plan for the project of “Development of the Ticketing System for RALS” is given in the tabular formal below,

Task Name

Duration

Start

Finish

Development of Ticketing System for RALS

154 days

Mon 1/1/18

Thu 8/2/18

   Conceptualization and project initialization

29 days

Mon 1/1/18

Thu 2/8/18

      Development of Project Charter

11 days

Mon 1/1/18

Mon 1/15/18

         Requirement Analysis

3 days

Mon 1/1/18

Wed 1/3/18

         Specification of Project is Evaluated

4 days

Thu 1/4/18

Tue 1/9/18

         Project Kick off meeting

4 days

Wed 1/10/18

Mon 1/15/18

      Vendor appointment

18 days

Tue 1/16/18

Thu 2/8/18

         Analysis of various vendors

4 days

Tue 1/16/18

Fri 1/19/18

         Capability analysis of vendors

5 days

Mon 1/22/18

Fri 1/26/18

         Budget Planning

5 days

Mon 1/29/18

Fri 2/2/18

         Planning Schedule

4 days

Mon 2/5/18

Thu 2/8/18

         Project is Initiated

0 days

Thu 2/8/18

Thu 2/8/18

   Ticketing system Design Phase

22 days

Fri 2/9/18

Mon 3/12/18

      Labour Management is planned

4 days

Fri 2/9/18

Wed 2/14/18

      System Design is made

5 days

Thu 2/15/18

Wed 2/21/18

      Initiation is built

6 days

Thu 2/22/18

Thu 3/1/18

      Milestone Requirements are formed

7 days

Fri 3/2/18

Mon 3/12/18

      Milestone: Design is completed of the Ticket System

0 days

Mon 3/12/18

Mon 3/12/18

   Implementation of the Ticketing system

36 days

Tue 3/13/18

Tue 5/1/18

      Implementing system designed

10 days

Tue 3/13/18

Mon 3/26/18

      Implementation Phase modification

8 days

Tue 3/27/18

Thu 4/5/18

      Requirement of design implemented

9 days

Fri 4/6/18

Wed 4/18/18

      Equipments are verified

9 days

Thu 4/19/18

Tue 5/1/18

      Milestone: Implementation is completed for Ticketing System

0 days

Tue 5/1/18

Tue 5/1/18

   Testing phase

30 days

Wed 5/2/18

Tue 6/12/18

      Initiation of testing phase

5 days

Wed 5/2/18

Tue 5/8/18

      Reporting the testing phase

1 day

Wed 5/9/18

Wed 5/9/18

      Reviewing the testing Phase

8 days

Thu 5/10/18

Mon 5/21/18

      Entire plan is developed

7 days

Tue 5/22/18

Wed 5/30/18

      Test Plan is developed

9 days

Thu 5/31/18

Tue 6/12/18

      Test result in executed

0 days

Tue 6/12/18

Tue 6/12/18

      Milestone: Final test results are formed

0 days

Tue 6/12/18

Tue 6/12/18

   Risk Management Phase

33 days

Wed 6/13/18

Fri 7/27/18

      Recognition of risk factors

5 days

Wed 6/13/18

Tue 6/19/18

      Risk Assessment

7 days

Wed 6/20/18

Thu 6/28/18

      Risk Mitigation

6 days

Fri 6/29/18

Fri 7/6/18

      Development of risk register

7 days

Mon 7/9/18

Tue 7/17/18

      Risk Impact is modified

8 days

Wed 7/18/18

Fri 7/27/18

      Milestone: Risk Management Plan is developed

0 days

Fri 7/27/18

Fri 7/27/18

   Project closure phase

4 days

Mon 7/30/18

Thu 8/2/18

      Success Evaluation of project

2 days

Mon 7/30/18

Tue 7/31/18

      Final Project report is developed

2 days

Wed 8/1/18

Thu 8/2/18

      Milestone: Project is closed

0 days

Thu 8/2/18

Thu 8/2/18

The WBS of the project of “Development of the Ticketing System for RALS” is shown in the table below,

WBS

Task Name

0

Development of Ticketing System for RALS

1

   Conceptualization and project initialization

1.1

      Development of Project Charter

1.1.1

         Requirement Analysis

1.1.2

         Specification of Project is Evaluated

1.1.3

         Project Kick off meeting

1.2

      Vendor appointment

1.2.1

         Analysis of various vendors

1.2.2

         Capability analysis of vendors

1.2.3

         Budget Planning

1.2.4

         Planning Schedule

1.2.5

         Project is Initiated

2

   Ticketing system Design Phase

2.1

      Labor Management is planned

2.2

      System Design is made

2.3

      Initiation is built

2.4

      Milestone Requirements are formed

M1

      Milestone: Design is completed of the Ticket System

3

   Implementation of the Ticketing system

3.1

      Implementing system designed

3.2

      Implementation Phase modification

3.3

      Requirement of design implemented

3.4

      Equipments are verified

M2

      Milestone: Implementation is completed for Ticketing System

4

   Testing phase

4.1

      Initiation of testing phase

4.2

      Reporting the testing phase

4.3

      Reviewing the testing Phase

4.4

      Entire plan is developed

4.5

      Test Plan is developed

4.6

      Test result in executed

M3

      Milestone: Final test results are formed

5

   Risk Management Phase

5.1

      Recognition of risk factors

5.2

      Risk Assessment

5.3

      Risk Mitigation

5.4

      Development of risk register

5.5

      Risk Impact is modified

M4

      Milestone: Risk Management Plan is developed

6

   Project closure phase

6.1

      Success Evaluation of project

6.2

      Final Project report is developed

M5

      Milestone: Project is closed

Part Four: Risk Analysis and Management Plan for RALS

System failure: System failure is the first ranked project risks that result in failing the operations of the project. The failure of the project would tend to imply the hindrance in the operations of the project. A detail of the risk is given below,

Ref no: RTF2001

Category: Technical

Triggers: System Flaws

Potential Responses: Preliminary testing and Prototyping

Risk Owner: IT Engineer

Probability: Likely

Impact: Critical

Financial Issues: Financial Issue is the second ranked project risks that result in failing the operations of the project. The failure of the project would tend to imply the hindrance in the operations of the project. A detail of the risk is given below,

Ref no: RTF2002

Category: Financial

Triggers: Insufficient resources in project

Potential Responses: Use of provisional resources

Risk Owner: Budgeter

Probability: Possible

Impact: Medium

Design Flaws: Design Flaws is the third ranked project risks that result in failing the operations of the project. The failure of the project would tend to imply the hindrance in the operations of the project. A detail of the risk is given below,

Ref no: RTF2003

Category: Technical

Triggers: Designing errors

Potential Responses: SDLC implementation for system designing

Risk Owner: Designer

Probability: Likely

Impact: Medium

Management Issues: Management Issues are the third ranked project risks that result in failing the operations of the project. The failure of the project would tend to imply the hindrance in the operations of the project. A detail of the risk is given below,

Ref no: RTF2004

Category: Operational

Triggers: Lack of the Strategic management framework

Potential Responses: Deploying strategic management structure in the project

Risk Owner: Project Manager

Probability: Possible

Impact: Medium

Delay in Project: Delay in Project is the third ranked project risks that result in failing the operations of the project. The failure of the project would tend to imply the hindrance in the operations of the project. A detail of the risk is given below,

Ref no: RTF2005

Category: Performance

Triggers: Issues in Project Management and Operations

Potential Responses: Deploying scheduling methods of project and system administration

Risk Owner: Planner

Probability: Almost Certain

Impact: Very Low

 Quality Management Plan

The association of RALS would incorporate the utilization of task advancement standards for building up the successful and enhanced administrations in the association with the assistance of Ticket System to be produced. The quality management plan is developed for integration of the effective operations for the project.

A set of verification activities: The quality affirmation can be checked by playing out a few tests like discovery testing comes about, UX testing, and execution testing.   

A set of validation activities: The quality affirmation can be confirmed by playing out a few activities like Identification of the Quality Issues, Development of Quality Management Plan, and Implementation of the Quality Management Plan

a. Annotated Bibliography

As characterized by Kendrick (2015), the undertaking comprises of various dangers and dangers. The examination of the different variables of hazard would have a tendency to enhanced the advancement of the venture administration ideas would be useful for the improvement of the hazard evaluation for the undertaking. The basic examination of the task advance would tend to utilize the administration of operations for the venture. Braglia and Frosolini (2014) have sent the utilization of the venture joining and its pertinence with the administration of the undertaking for data framework improvement. The advancement of the venture for the execution of the data framework would contain the administration of the operations and its arrangement with the framework improvement. The investigation of the article by Stark (2015), would help in building up some arrangement for the change of the operations and creating successful correspondence for the operations of the venture. The examination of the diverse factors of risk would tend to upgraded the headway of the endeavour organization thoughts would be valuable for the change of the danger evaluation for the undertaking. The essential examination of the venture progress would have a tendency to use the organization of operations for the assignment.

  1. Successful finishing the task in assessed time
  2. Following the task spending plan and asset
  3. Meeting the extents of the task

Bibliography

Amrollahi, A., Ghapanchi, A. H., &Talaei-Khoei, A. (2014). Three decades of research on strategic information system plan development.Communications of the Association for Information Systems, 34(1), 84.

Braglia, M., &Frosolini, M. (2014).An integrated approach to implement project management information systems within the extended enterprise.International Journal of Project Management, 32(1), 18-29.

Coronel, C., & Morris, S. (2016). Database systems: design, implementation, & management. Cengage Learning.

Galliers, R. D., &Leidner, D. E. (2014). Strategic information management: challenges and strategies in managing information systems. Routledge.

Garton, C., & McCulloch, E. (2012). Fundamentals of Technology Project Management. MC Press, LLC.

Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational excellence.pearson.

Hubicki, M. (2014). Risk Management Plan.

Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-proofing your project. AMACOM Div American Mgmt Assn.

Nanda, V. (2016). Quality management system handbook for product development companies.CRC Press.

Pritchard, C. L., & PMP, P. R. (2014). Risk management: concepts and guidance. CRC Press.

Schwalbe, K. (2015). Information technology project management.Cengage Learning.

Stark, J. (2015). Product lifecycle management.In Product Lifecycle Management (pp. 1-29).Springer International Publishing.

Verburg, R. M., Bosch-Sijtsema, P., &Vartiainen, M. (2013).Getting it done: Critical success factors for project managers in virtual work settings.International Journal of Project Management, 31(1), 68-79.

Verzuh, E. (2015). The fast forward MBA in project management.John Wiley & Sons.

Get An Awesome Price Quote For Your Paper – Absolutely FREE!
    Add File
    Files Missing!

    Please upload all relevant files for quick & complete assistance.

    Our Amazing Features

    delivery

    No missing deadline risk

    No matter how close the deadline is, you will find quick solutions for your urgent assignments.

    work

    100% Plagiarism-free content

    All assessments are written by experts based on research and credible sources. It also quality-approved by editors and proofreaders.

    time

    500+ subject matter experts

    Our team consists of writers and PhD scholars with profound knowledge in their subject of study and deliver A+ quality solution.

    subject

    Covers all subjects

    We offer academic help services for a wide array of subjects.

    price

    Pocket-friendly rate

    We care about our students and guarantee the best price in the market to help them avail top academic services that fit any budget.

    Getting started with MyEssayAssignmentHelp is FREE

    15,000+ happy customers and counting!

    Rated 4.7/5 based on
    1491 reviews
    ;