ITC505 ICT Project Management

Published : 27-Sep,2021  |  Views : 10

Question:

Prepare a Assessment based on the Virtucon/Globex scenario, and your peer to peer learning from Assessment You are required to develop a charter for the Project including Include the Project description and overview you developed as part of Assessment.

Identify the desired area of impact - Rank the following areas in terms of importance: Strategy / Customer / Financial / Operational / Social With reference to your project, identify one or two of the following types of value:

Develop an appropriate metric - this sets the target and expectation of all the stakeholders. It is important to determine a quantitative target that needs to be expressed as a metric in terms of an increase or decrease of money.
Determine the timeframe for achieving the MOV - ask yourselves, when do we want to achieve this target metric.

Answer:

The strategy, customer, financial, operational, and social is the desired area of impact for the RALS ticket system development project. These factors are explained below,

Area of impact

Description

Ranking

Financial

the money related framework can be clarified as the operations of the procedures for the improvement of the operations for coordinating the advancement of the operations and suggesting the consummation of the undertaking

1st

 

Customer

the customers can be comprehended as the framework range of raising different sorts of questions brought by the general population up in connection to the framework and task created for RALS

2nd 

Operational

the operational procedures would be inferred for shaping the security of the operations and its reconciliation of the procedure for the adjustment of the procedures of the association4th

3rd 

Strategy

the strategy can be characterized for affecting the operations of the venture of RALS by building up some successful and enhanced operations

4th 

Social

the operational procedures would be suggested for building up the security of the operations and its combination of the procedures

5th 

 o Better – The RALS venture had seen the advancement of another framework for expanding the proficiency of work by data administration

o Faster – The RALS undertaking would help in incorporating the operations of the venture and advancement of the expanded speed of operations

o Cheaper – The RALS task would help in dealing with the data on a solitary database and subsequently it would diminish the general cost of the data framework administration

o Do more – The framework usage at RALS would incorporate the data of the RALS and it would help in building up the more intelligent procedures of the association.

Rank

Impact

Metrics

Timeframe

1

Financial

Money Profit and Revenue era

6 months

2

Customer

Number of clients returning to the association for their administrations

2 months

3

Operational

Less Consumption of time for the finishing of the hierarchical operations

2 months

4

Strategy

The volunteers would get followed because of the utilization of the framework created in RALS

1 month

5

Social

Volunteers would have the capacity to get associated with the clients

3 months

 Define Scope and produce a Scope Management Plan

Scope Definition: The undertaking of RALS Ticketing System advancement would help in building up the change of the operations of the Globex for following client's and volunteer's data by the assistance of framework created.

Requirements: The requirements of the project include both project team and materials for the development of the project operations. The requirements of the project are. 

In-scope and out of scope items of the project: The in-scope things of the RALS venture are get ready for the operations of the undertaking, improvement of the RALS Ticketing System, increment of effectiveness of the administration of the data about volunteers, and helping for operational and key advancement. The out of degree things of the RALS venture incorporate upkeep exercises, conveyance of the materials, and preparing of the labourers in Globex

Deliverables of the project: The deliverables for the RALS venture are,

  1. Project Plan and Resource Allocation Plan
  2. Project Documents including Initiation and Charter Documentation
  3. Scope Verification Plan
  4. System Design and Implementation Plan
  5. Testing Results

Resource Name

Tasks

Budgeter

   Client's requirement is analyzed

   Budget for the project is developed

   Outsourcing of the project materials

Computer Devices

   Installing hardware components

Documenter

   Making Initiation documents

   Charter documentation

   Making final documents

   Review of documents

IT Engineer

   Storage is developed

   Transfer of the data

   Design analysis for the ticket system

   Development of User interface

   Coding and programming is done

   Integration of ticket system with storage

   Installing hardware components

Network Components

   Installing hardware components

Planner

   Project team is selected

   Plan methodology is selected

   Outline for the plan is developed

Project Manager

   Analysis of the project feasibility

   Requirement Analysis

   Project Meetings are held

   Signing off the documents

   Review of the plan

   Signing off the documents

Storage

   Storage is developed

System Analyst

   Design Platform is selected

   Outline for the design is developed

   Prototype is developed

   Review of the prototype

   Simulation of the completed design

Tester

   Black box testing

   UX testing

   Operations and tested

   white box testing

Wireless routers

   Installing hardware components

 

Resource Name

Type

Initials

Std. Rate

Budgeter

Work

B

$60.00/hr

Computer Devices

Material

C

$1,740.00

Documenter

Work

D

$60.00/hr

IT Engineer

Work

I

$95.00/hr

Network Components

Material

N

$970.00

Planner

Work

P

$60.00/hr

Project Manager

Work

PM

$100.00/hr

Storage

Material

S

$2,320.00

System Analyst

Work

SA

$90.00/hr

Tester

Work

T

$85.00/hr

Wireless routers

Material

W

$870.00

Project Plan

WBS

Task Name

Duration

Start

Finish

Resource Names

Cost

1.1

      Analysis of the project feasibility

3 days

Mon 10/2/17

Wed 10/4/17

Project Manager

$2,400.00

1.2

      Requirement Analysis

5 days

Thu 10/5/17

Wed 10/11/17

Project Manager

$4,000.00

1.3

      Making Initiation documents

4 days

Thu 10/12/17

Tue 10/17/17

Documenter

$1,920.00

1.4

      Charter documentation

3 days

Wed 10/18/17

Fri 10/20/17

Documenter

$1,440.00

1.5

      Project Meetings are held

1 day

Mon 10/23/17

Mon 10/23/17

Project Manager

$800.00

1.6

      Signing off the documents

1 day

Tue 10/24/17

Tue 10/24/17

Project Manager

$800.00

2.1

      Client's requirement is analyzed

5 days

Wed 10/25/17

Tue 10/31/17

Budgeter

$2,400.00

2.2

      Project team is selected

7 days

Wed 11/1/17

Thu 11/9/17

Planner

$3,360.00

2.3

      Budget for the project is developed

4 days

Fri 11/10/17

Wed 11/15/17

Budgeter

$1,920.00

2.4

      Outsourcing of the project materials

3 days

Thu 11/16/17

Mon 11/20/17

Budgeter

$1,440.00

3.1

      Plan methodology is selected

2 days

Tue 11/21/17

Wed 11/22/17

Planner

$960.00

3.2

      Outline for the plan is developed

5 days

Thu 11/23/17

Wed 11/29/17

Planner

$2,400.00

3.3

      Review of the plan

3 days

Thu 11/30/17

Mon 12/4/17

Project Manager

$2,400.00

4.1

      Design Platform is selected

1 day

Tue 12/5/17

Tue 12/5/17

System Analyst

$720.00

4.2

      Outline for the design is developed

3 days

Wed 12/6/17

Fri 12/8/17

System Analyst

$2,160.00

4.3

      Prototype is developed

7 days

Mon 12/11/17

Tue 12/19/17

System Analyst

$5,040.00

4.4

      Review of the prototype

2 days

Wed 12/20/17

Thu 12/21/17

System Analyst

$1,440.00

4.5

      Simulation of the completed design

3 days

Fri 12/22/17

Tue 12/26/17

System Analyst

$2,160.00

5.1

      Storage is developed

10 days

Wed 12/27/17

Tue 1/9/18

IT Engineer, Storage[1]

$9,920.00

5.2

      Transfer of the data

5 days

Wed 1/10/18

Tue 1/16/18

IT Engineer

$3,800.00

5.3

      Design analysis for the ticket system

4 days

Wed 1/17/18

Mon 1/22/18

IT Engineer

$3,040.00

5.4

      Development of User interface

6 days

Tue 1/23/18

Tue 1/30/18

IT Engineer

$4,560.00

5.5

      Coding and programming is done

12 days

Wed 1/31/18

Thu 2/15/18

IT Engineer

$9,120.00

5.6

      Integration of ticket system with storage

8 days

Fri 2/16/18

Tue 2/27/18

IT Engineer

$6,080.00

5.7

      Installing hardware components

7 days

Wed 2/28/18

Thu 3/8/18

IT Engineer, Computer Devices[1], Network Components[1], Wireless routers[1]

$8,900.00

6.1

      Black box testing

5 days

Fri 3/9/18

Thu 3/15/18

Tester

$3,400.00

6.2

      UX testing

5 days

Fri 3/16/18

Thu 3/22/18

Tester

$3,400.00

6.3

      Operations and tested

5 days

Fri 3/23/18

Thu 3/29/18

Tester

$3,400.00

6.4

      white box testing

5 days

Fri 3/30/18

Thu 4/5/18

Tester

$3,400.00

7.1

      Making final documents

3 days

Fri 4/6/18

Tue 4/10/18

Documenter

$1,440.00

7.2

      Review of documents

2 days

Wed 4/11/18

Thu 4/12/18

Documenter

$960.00

7.3

      Signing off the documents

1 day

Fri 4/13/18

Fri 4/13/18

Project Manager

$800.00

Risk Analysis and Management Plan for RALS

No.

REF001

REF003

REF03

REF004

REF005

Rank

1st 

2nd 

3rd 

4th 

5th 

Risk

System Failure

Over budgeting

Design flaws

Management Issue

Delay in completion

Description

Framework disappointment may be come about when the ticketing arrangement of RALS would neglect to build up the compelling handling of the data for building up the change factors

The exercises of the venture may wind up in causing overabundance use of the undertaking assets which may prompt the over planning of the task by

The issues of the plan made for the ticketing framework would be a noteworthy hazard factor that could bring about shaping the defeat of the undertaking 2013

Choosing a precise plan procedure for the venture

The issues in administration is a main consideration for the improvement of the obstacles in the finishing of the undertaking

Category

Technical

Financial

Technical

Operational

Performance

Triggers

Flaws in system

Lack of Adequate Resources

Absence of Design Methodology

Lack of Management Approach

The project would tend to form the development of the issues in successful completion of the project operations

Potential Responses

Earlier testing of the framework before execution

Advancement of temporary spending plan for the task

Choosing a precise plan procedure for the venture

improvement of the obstacles in the finishing of the undertaking

Utilization of undertaking administration standards and operations

Risk Owner

IT Engineer

Budgeter

Designer

Project Manager

Planner

Probability

Likely

 

Possible

Likely

Possible

Almost certain

Impact

Critical

Medium

Medium

Medium

Low

 Quality Management Plan

The quality management plan for RALS project includes,

Stage 1: Identification of the quality issues

Stage 2: Analysis of the quality issues and their effect on venture

Stage 3: Development of alleviation techniques

Stage 4: Monitoring the actualized techniques

Stage 5: Reviewing the arrangement

a. Annotated Bibliography

As indicated by researchers like Amrollahi, Ghapanchi and Talaei-Khoei (2014), the task administration can be produced by following the particular vital administration strategies. The techniques and procedures created for the task administration would be useful for coordinating the advancement of the enhanced procedures and capacities inside the association.

Then again researchers like Galliers and Leidner (2014), the key administration confront the issue of dealing with the venture effectively because of the slack of the data handling and improvement. It would be very required for the advancement of the enhanced innovation and spontaneous creation for adjusting the capacities for the venture.

Consequently, from the investigation of Stark (2015), it can be inferred that the item life cycle administration can be suggested for building up the operations of the venture. It is likewise conceivable that the utilization of the undertaking administration standards would help in covering the real effect of the framework improvement models.

b. Checklist for RALS project

Checklist Item

Checked

Advancement of the Project Plan

?

Improved Resource Allocation Plan

?

Closing down the Project Documents including Initiation and Charter Documentation

?

Viable System Design

?

Well ordered usage design

?

Expected Test comes about

?

 C. Evaluation Criteria

  1. Project Plan and Resource Allocation Plan
  2. Project Documents including Initiation and Charter Documentation
  3. Scope Verification Plan
  4. System Design and Implementation Plan
  5. Testing Results

Bibliography

Amrollahi, A., Ghapanchi, A. H., &Talaei-Khoei, A. (2014). Three decades of research on strategic information system plan development.Communications of the Association for Information Systems, 34(1), 84.

Braglia, M., &Frosolini, M. (2014).An integrated approach to implement project management information systems within the extended enterprise.International Journal of Project Management, 32(1), 18-29.

Coronel, C., & Morris, S. (2016). Database systems: design, implementation, & management. Cengage Learning.

Galliers, R. D., &Leidner, D. E. (2014). Strategic information management: challenges and strategies in managing information systems. Routledge.

Garton, C., & McCulloch, E. (2012). Fundamentals of Technology Project Management. MC Press, LLC.

Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational excellence.pearson.

Hubicki, M. (2014). Risk Management Plan.

Kami, N. (2015). U.S. Patent No. 9,116,916. Washington, DC: U.S. Patent and Trademark Office.

Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-proofing your project. AMACOM Div American Mgmt Assn.

Nanda, V. (2016). Quality management system handbook for product development companies.CRC Press.

Pritchard, C. L., & PMP, P. R. (2014). Risk management: concepts and guidance. CRC Press.

Schwalbe, K. (2015). Information technology project management.Cengage Learning.

Stark, J. (2015). Product lifecycle management.In Product Lifecycle Management (pp. 1-29).Springer International Publishing.

Tornabene, C., Hussain, M. M., Crowe, T., Cohen, N., & Panzer, J. (2012).U.S. Patent No. 8,103,729. Washington, DC: U.S. Patent and Trademark Office.

Verburg, R. M., Bosch-Sijtsema, P., &Vartiainen, M. (2013).Getting it done: Critical success factors for project managers in virtual work settings.International Journal of Project Management, 31(1), 68-79.

Verzuh, E. (2015). The fast forward MBA in project management.John Wiley & Sons.

Get An Awesome Price Quote For Your Paper – Absolutely FREE!
    Add File
    Files Missing!

    Please upload all relevant files for quick & complete assistance.

    Our Amazing Features

    delivery

    No missing deadline risk

    No matter how close the deadline is, you will find quick solutions for your urgent assignments.

    work

    100% Plagiarism-free content

    All assessments are written by experts based on research and credible sources. It also quality-approved by editors and proofreaders.

    time

    500+ subject matter experts

    Our team consists of writers and PhD scholars with profound knowledge in their subject of study and deliver A+ quality solution.

    subject

    Covers all subjects

    We offer academic help services for a wide array of subjects.

    price

    Pocket-friendly rate

    We care about our students and guarantee the best price in the market to help them avail top academic services that fit any budget.

    Getting started with MyEssayAssignmentHelp is FREE

    15,000+ happy customers and counting!

    Rated 4.7/5 based on
    1491 reviews
    ;